CATS to updat actual cost to cost activity
Hi, updating employees in CATS with WBS will produce actual cost in WBS, however the CATS with network and activity is not producing actual cost in activity rather it is only producing confirmation....
View ArticleRong/False Booking of Costs on CO.Object WBS-Element
Hi All, from time to time make the business department a mistake by the Posting of the costs on the WBS-element. They choice the the rong wbs-element. Now can we repost/rebook this cost on the right...
View ArticleSettlement Rule against NWA
Hi Is there a report of some sort where I can view the settlement rule against the NWA for a project or a suite of projects? We are checking settlement rules as there are some who drag and drop NWA in...
View ArticleBudget Return Through IM-PS
Hi PS gurus, Please assist me on one issues related with budget return here IM budget has interface with PS.We have done Budget Carry Forward from 2014 to 2015 by CJCO transaction. After some time...
View Articleconcept of backflush in material
Hi experts,can anybody explain me what is Backflushing and when we should use this tick ? ThanksAshis
View ArticleResults Analysis
Hello Every body, I am new to SAP. Can anyone advise me towards some useful information on Results Analysis, Am aiming to understand Results Analysis from SAP Cost Controlling perspective and how the...
View ArticleSAP PPM and PS for projects involving several plants
Hello, I am investigating the possibility to plan and control the development costs at the company with the SAP PS or PPM. Thus, the goal was having team members booking their labor hours to the...
View ArticlePrimavera - SAP Interface/ integration
Hi, I Need some information and help related to Primavera - SAP Interface/ integration. 1. what are the Prerequisites? 2. How it works - means how data will get transferred from primaver to SAP? 3....
View ArticleCAT2 posting
Hello friends, Request your inputs for my queries below- 1 1. Once we post timecards in CAT2 against to a WBS, we can see actual costs booked against to the same WBS in CJI3. Then how exactly, the...
View ArticleCapitalization and Expense on same SAP PS Project
SAP PS Gurus, I have a requirement to show capitalized, expense, R&D, in the same project. Currently, we have a standard project def with the appropriate settlement profile assigned for each...
View ArticleDetails of actual budget consumed against WBS
i want a report that should display the details of actual budget consumed against the WBS, just like when we run Tcode:S_ALR_87013558 and select GOTO>>Line Items>>Project commitment line...
View ArticleDIP: Each WBS in 1 line at the DMR order - how to?
Hi' I hope some of you can help us Our solution:* Material A is added at Contract i VA41 *A project with network and activities is created automatically (assembly processing) *The project are changed...
View ArticlePrimavera - SAP Interface/ integration
Hi, I Need some information and help related to Primavera - SAP Interface/ integration. 1. what are the Prerequisites? 2. How it works - means how data will get transferred from primaver to SAP? 3....
View Articleconcept of backflush in material
Hi experts,can anybody explain me what is Backflushing and when we should use this tick ? ThanksAshis
View ArticleResourse allocation to project WBS
SAP Gurus, I am working on a project to replace Primavera with CA PPM for PLC. Resources will be assigned in CA PPM and sent to SAP via integration interface. In order for the resources to enter...
View ArticleDetails of actual budget consumed against WBS
i want a report that should display the details of actual budget consumed against the WBS, just like when we run Tcode:S_ALR_87013558 and select GOTO>>Line Items>>Project commitment line...
View ArticleExplosive BOM
Hi Experts, I have configured BOM transfer, i created Material BOM maintained reference point for all material and maintained reference point in network activity also. then i gone through CN33...
View ArticleSAP PS year End closing
HI Experts,other than investment projects (PS & IM) ,we also have R&D projects which are purely expenses and we don't have any IM program for expenses.We directly Budjet in CJ30.can anybody...
View ArticleCut Over Stratergy
Dear All,We are going to fix cut over stratergy for go-live, but i as per requirement, i need to capture all historical costs and revenues (which were inccured in legacy system) into SAP. So i have...
View ArticleAA617 Acquisition Value Negative in area 01
Hi, We are getting the above error message while executing a AuC-Fixed Asset final settlement for a few WBS Elements using CJ88. encountered problem when trying to settle WBS elements for two projects,...
View Article