DIP: Each WBS in 1 line at the DMR order - how to?

$
0
0

Hi'

 

I hope some of you can help us

 

Our solution:

* Material A is added at Contract i VA41

 

*A project with network and activities is created automatically (assembly processing)

 

*The project are changed to fit each delivery - end up with 2-30 WBS-elements

 

*CATS-confirmations at the network activities are created in CAT2 and transferred to the project through CAT5

 

*DP91 capture CATS-confirmations with activity type A = material A, B = material B and C = material C (material determination)

The DMR contain 1 line item per activity type

 

Now we would like the DMR to have these line items:

 

WBS 1 with activity type A

WBS 1 with activity type B

WBS 1 with activity type C

WBS 2 with activity type A

WBS 2 with activity type B

WBS 2 with activity type C

WBS 3 with activity type A

and so on.

 

How can we solve this issue?

The WBS-elements have different names for each project. We had not succes to create a Set reflecting this.

How can we make the setup resulting in the mentioned DMR line items.

 

I hope for some input.

Thank you in advance

 

Regards

Lone


Viewing all articles
Browse latest Browse all 1010

Trending Articles



<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>