Unable to get final receiver in CJ88 (wip settlement) test run
Hi, We are doing WIP for MTO scenario.Actual costs should be shown as WIP and we are able to get required WIP using KKA2. However test run of CJ88 does not show the final receiver (in billing wbs...
View ArticleGenerate PR from stock item in network activity - PS
Dear Experts, I have two points in PS:I want to generate PR from stock material on PS activity.I want only PR but system will generate reservation as well when assigning stock item. I have configured...
View ArticleBudget Exceeded Error even after budget available in in CJ30
Dear All Experts, I have configured the PS-Budget. While creating PO I am getting below error Item 010 WBS element PCS-0012 budget exceeded Message no. BP603 DiagnosisBudget was exceeded by 100,00...
View ArticlePeculiar error message after doing first wip settlement for project
Hello, I am trying to do WIP for project and settle it. (Make To Order) scenario. Sales order item is linked to project WBS for revenue. Material consumption (backflush - 281 movement type) and...
View ArticleUnable to do final settlement WIP - results analysis - in a project
Hello All, We have set RA for projects. This is MTO scenario. All actual costs of project in Release status are calculated as WIP in top WBS.For periodic settlement, this is getting settled to B/S and...
View ArticleChange Log For WBS Element
Hi Can you please inform me the how to get what are the changes which have happened on the WBS Element Master Data..... ( Just like we can get for vendor or Customer) RegardsAshwin
View ArticleAppropriation Request Error - Create Measure Not Allowed
Hello All Experts, I am trying to create measure by clikcing on Order Button but when I am clicking on Order I am getting below error - I tried seaching all the status profile which are assigned to...
View ArticlePR or PO not triggering activation control as per the set tolerance limit
Hi, I created as belowProject - 100008 (without investment program ID) - StandardWBS (level-1) - 1000081WBS (level-2) - 1000082WBS (level-3) - 1000083 CJ30 - created overall budget - $1000. Created PO...
View Articlesystem issue during budget check commitment item
Dear PS experts, while attaching a material to a specific activity the budget have to check the PR value as i activate commitment management in controlling area.but i have an issue as when the...
View ArticleRestrict user for changing and release budget for level 1 WBS
HI Experts, Can anyone help me through this - I want to restrict some user to change in level 1 wbs budget either original or release.For e.g. below is the WBS structure of my projectC-15TST01...
View ArticleUserfield Character Lenght
Hi, We are trying to increase the character length of User field from 20 characters to 24 characters? Are there any User-exit to do so?
View ArticleWBS variant similar to Network Variant
I have a big standard wbs with multiple standard wbs. now when i create the operative project, i include the std wbs. i keep the relevant elements and delete others. i want to automate this feature....
View Articleconcept of backflush in material
Hi experts,can anybody explain me what is Backflushing and when we should use this tick ? ThanksAshis
View ArticleRestrict user for changing and release budget for level 1 WBS
HI Experts, Can anyone help me through this - I want to restrict some user to change in level 1 wbs budget either original or release.For e.g. below is the WBS structure of my projectC-15TST01...
View ArticleSettlement Rules
Hi All, I am new to PS. Does anyone know any bapi/fm for Settlement rules, for getting details and upload Regards
View ArticleDetails of actual budget consumed against WBS
i want a report that should display the details of actual budget consumed against the WBS, just like when we run Tcode:S_ALR_87013558 and select GOTO>>Line Items>>Project commitment line...
View ArticleSAP PS S_ALR_87013611 report
Hi,We want to see WBS element in this report.When I click on the 'Actual Line Item' ,I see costs at Network Activities level since we use NWA to capture costs.Can we add corresponsidng WBS element...
View ArticleBudget Exceeded Error even after budget available in in CJ30
Dear All Experts, I have configured the PS-Budget. While creating PO I am getting below error Item 010 WBS element PCS-0012 budget exceeded Message no. BP603 DiagnosisBudget was exceeded by 100,00...
View Articleproblem in translation
HiI need to change the word "Internal Processing" when creating new activity in a project. I did anything that I knew but it didn't affect. Can anyone help me? Regards
View ArticleHow to get Customer for all the WBS Element postings
Hi All, I am tryng to get Customer associated with any WBS posting in PS. The effort I have done for this is as below; 1. Took OBJNR from PRPS for the required WBS Elements from CJI3 output.2. Passed...