Hi, When we are going to settle a WBS element, system throws an error "First settle items from previous year in previous year 2011: 400751376/001" message no. AW624. The obvious reason is there are...
View ArticlePS Network & activity Table related with PO
Hello experts , I need a table name which will give me the details of 1) Network is a primary key and related to it the list of activity numbers . 2) now I also need to link these with PO number ???...
View ArticleValidation for WBS field Length
Dear All, I am using following Project coding mask T.00.XXX.000.000.00.00.0 Where Project code- T.00.XXX.000Level 1 WBS -T.00.XXX.000.000Level 2 WBS-T.00.XXX.000.000.00Level 3WBS-...
View ArticleTable to find system status
Dear All, I need a table where I can see the status of the Project/WBS. The system statuses are available in table TJ02, how can i link this with a particular project and WBSE? Thanks & Regards, VDS
View ArticleProject System Configuration
Hi All,I am new to Project System. 1. Can any tell me what is Project, WBS Element, Network and Activity....2. Please tell me step by step configuration of PS module.3. Please tell me the flow of how...
View Articleconcept of backflush in material
Hi experts,can anybody explain me what is Backflushing and when we should use this tick ? ThanksAshis
View ArticleBeginner need advice for PS table
Dear All, Kindly advice the function and name of PS table that are normally use in PS module. Such as PRPS,PROJ,AUFC. Many thanks in advance. Nies
View ArticleWBS element master data - T-code.
Dear All, Can any one of you tell me, whether there is any t-code to see wbs element master data( not table, my user dont have access), to see WBS element and Responsible cost center. CJ43N is not...
View ArticleBudget,Actual and committment costs..
I am working on a z report since long time, My requirement is to get budget, actual cost, committment cost, advances in the Z report. I provided data to Abaper with OBJNR to BPGE table and retrieve the...
View ArticleWBS settlement with Result Analysis Key
Hi PS expert, Ok, here is my requirements from business people. We have project for making custom specification equipment for selling. We are charging costs such as materials, labor, and expenses to...
View ArticleCJI3 report
Hi, I'm trying to find out the unsettled value in a WBS through CJI3. But I'm not able to segregate all these line items. So please let me know, how to use layout/filter to find out this. With...
View ArticleAutomatic generation of settlement rule not working for all wbs elements
Hello, Can anyone help with this. I have noticed that when I create and release me project and generate settlement rules, not all the WBS elements have their settlement rules generated. As such, when...
View ArticleRPSCO and COSS tables
Dear friends, I wanted to know the difference between RPSCO and COSS tables In terms of the values they store majorly, also appreciate if provide some info on the other cost tables like COES,COEP, COSP...
View ArticleWBS to AUC settlement
Hi, When we are going to settle a WBS element, system throws an error "First settle items from previous year in previous year 2011: 400751376/001" message no. AW624. The obvious reason is there are...
View ArticleHow to View Vendor wise Payment against WBS element
Hi, Project requirement is to ....to view Vendor wise payment against WBS element.... i have checked standard PS reports like CJIA,S_ALR_********.....,Transaction from FI FBL1n but nothing is...
View ArticleS_ALR_87013542 Report
Hi All, I have created a report having all the parameters same as the standard S_ALR_87013542. According to the requirement I have expanded only the Cost Element instead of WBS as in standard. Report...
View ArticleWBS to AUC settlement
Hi, When we are going to settle a WBS element, system throws an error "First settle items from previous year in previous year 2011: 400751376/001" message no. AW624. The obvious reason is there are...
View ArticlePrimavera - SAP Interface/ integration
Hi, I Need some information and help related to Primavera - SAP Interface/ integration. 1. what are the Prerequisites? 2. How it works - means how data will get transferred from primaver to SAP? 3....
View ArticleResults Analysis
Hello Every body, I am new to SAP. Can anyone advise me towards some useful information on Results Analysis, Am aiming to understand Results Analysis from SAP Cost Controlling perspective and how the...
View ArticleStrategy for approval of projects (PS)
Good afternoon my friends. Once again I'm here to ask for your help. I am new in module project system (PS) and would like to know if there is a way to create strategies realese for projects (CJ20N) or...