Material components in SAP PS

$
0
0

Hello Experts,

 

I have got confused with two things while assigning a material to a NWA.

 

Confusion between 1) Procurement type and 2) Indiv./Collect Indicator in Proc. Param tab.

 

When I gave Indiv./Collect Indicator as 2 in MRP4 tab of material master it is taking as reservation for Network and when it is either space of 1 it is taking reservation for WBS.

 

When it is for WBS then Value Flow/Quantity Flow screen all the fields are updated. (Acct Assign Cat as Q, Special Stock as Q, Valuation as M etc..)

 

When it is for Network No fields are updated.

 

When I run MD51 it is creating planned orders when Indiv/Collec is space or 1 and is not generating when it is space.

 

Questions

 

1) Is Procurement type and Indiv/Collect Indicator interrelated ? (I am feeling Yes - Need confirmation)

2) Is there any config ar any logic for the values in Value Flow/Quantity Flow screen ? (Acct Assign Cat as Q, Special Stock as Q, Valuation as M etc)

     a) How is it coming for Reservation for WBS ?

     b) Can we get the same for Reservation for network by doing any config change ?

3) Can we run MD51 and generate the planned orders from reservations when procurement parameter is Reservation for Network ? If so how?

 

Thanks