Our projects relate to the completion of a business jet for a given client. All of the work associated with the project is specific to the client; however, some of the work is carried out on the physical aircraft and must remain associated with that aircraft while other work can "follow" a customer to another aircraft if for some reason there is a need to re-assign the customer from one aircraft to another (this is a regular occurrence).
In our proposed project systems environment, level 2 of the WBS provides parent elements for these two categories of work. One is referred to as S/N (aircraft specific); the other, as D/N (customer specific). Below this, our WBS is object oriented. We use network orders to address complex assembly manufacturing. We use production orders (PP) to address detail parts. Both represent / include activity that is account assigned to the lowest level of the WBS which can roll up to either the S/N or D/N side of the project. Work is only posted to this lowest WBS level.
When a customer is re-assigned to a different aircraft, this is done in reciprocal or independent project pairs. When this happens, I need to move the S/N parent and children to a different project. All related data / postings needs to be realigned to the new project.
This appears to be possible BEFORE actuals post to any S/N WBS children. Is it possible to do this AFTER postings occur? Will all data / related posting follow the WBS move?