I have trouble about shifting activity, i try to imitate function ms.project automatic reschedule.
Act Start Finish
Activity10 02.11.2015 03.11.2015
Activity20 04.11.2015 05.11.2015
Relation between activity FS, Activity 20 as successor.
I try to extend finish date activity10 through CJ2B to 10.11.2015.
why activity20 did not reschedule to 11.11.2015(Start) 12.11.2015(Finish)?
please can someone help me to give me solution, what should i do?
best regards,
michael a