Quantcast
Channel: SCN : Popular Discussions - SAP Project Systems (SAP PS)
Viewing all articles
Browse latest Browse all 1010

Unable to get Progress Analysis values

$
0
0

Hi All,

 

I am trying to get Progress Analysis of a test project.

Following steps done

 

1. Created project - WBS, N/W with activity costing

 

2. All internal activities - Activity type = Labour - same workcenter, only Quantity is different

 

3. Plan cost and Budget done, Project Released

 

4. SKF for Progress -- PS:NonAgg %, PS:Agg. %, PS:Completion % for RA

 

5. Assigned SKF to value categories

 

6. Progress Version "100", Checked both Plan and Actual checkboxes

EV basis - Cost plan (active project, overall values)

Percentage of Completion -- POC Weighting Cost plan (active project, total values)

Planning type - Basic Dates

Early/Late - Earliest possible

Checked both Actual Method and Ref. plan. meth.

 

7. Cost Element 9600001 assigned

 

8. In the project, all internal activities set with Measurement Method as Cost Proportionality for PLan and Degree of Processing from Confirmation for Actual.

POC weight set as 1 (I do not intend to set any weight but since EV not getting calculated, I tried setting this as 1)

 

9. Confirmed 2 int. activities twice with 5% confirmation.

 

10. Executed tcode CNE1

 

11. Executed CNE5 - see below screen shot. I do not see any EV variable values

 

CNE5 Progress Analysis Overview.png


Viewing all articles
Browse latest Browse all 1010

Trending Articles



<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>