Dear All,
how to define selection Variant in CNE2 (Tcode) collective Processing.
Actually I Create a Selection Variant for 20 Selected Projects. by tick on Only for background processing and save the variant. and then I run the project progress. but it give 0 in CNE5 project progress. while when i run CNE1 for these projects it shows progress.
Thanks
Govind