Hi all,
I have a problem when run MRP for PS by MD51. I have a project structure below:
Project definition: K-52
1.WBS element: K-52-01
Network: 101
Activity: 101 - 10 (material A, quantity = 10)
2.WBS element: K-52-02
Network: 102
Activity: 102 - 10 (material A, quantity = 25)
WBS element: K-52-02-01
Network: 103
Activity: 103 - 10 (material A, quantity = 15)
WBS element: K-52-02-02
Network: 104
Activity: 104 - 10 (material A, quantity = 25)
Each activity, I choose generate reservation instead of PR directly.
1. When I run MRP by MD51 for project definition K-52, the system generated 4 planned order for material A of each activity. This's no problem
2. When I run MRP by MD51 for WBS element K-52-01, the system generated 4 planned order for each activity like when I run MRP for project definition. I just want run MRP for WBS element K-52-01, but I don't know what happen and how to fix it. This's the first problem.
3. When I run MRP by MD51 for WBS element K-52-02, the system generated 2 planned or ther for K-52-01 and K-52-02, I don't know how system generate planned order for K-52-01. This's the second problem.
4. When I run MRP for WBS element K-52-02-01, the system generated 2 planned or ther for K-52-01 and K-52-02-01, I don't know how system generate planned order for K-52-01. This's the third problem
5. When I run MRP for WBS element K-52-02-02, the system generated 2 planned or ther for K-52-01 and K-52-02-02, I don't know how system generate planned order for K-52-01 as like as run mrp for K-52-02-01 above. This's the fourth problem
How I fix that, hopping your support.
Thanks
Regard
Hoai Vu