Dear All,
I am using "Cost Proportional" method for Progress Analysis. When i am executing the progress analysis (CNE1) for a project, system is adding the planned cost of Production orders into BCWS, which are created with reference to project . Because of which the BCWS value is showing more than the Planned Cost Sch 000 value in CNE5 report.
So please let me know is this a standard behavior of system?
If Yes, please let me know is there any way to exclude these planned values of production orders from Progress Analysis calculation.
Thanks & Regards,
Rao.