Question With Actual Costs

$
0
0

Hi espert,

 

I have a problem with the Actual costs about a specific WBE element.

 

In the output of the  report 12KST1A the amount of the actual is different from the details lines item.

 

In the Table RPSCO there is three record of the actual , while after I have run the transaction CJEN the system return me 4 record of ACTUAL Costs.

 

After i go in table RPSCO and I see again 3 Record of ACTUAL COST.

 

The problem will be solved if also the 4 lines that i see after that i run the transaction code CJEN was stored in the RPSCO.

 

How i Can solve my problem? How it is possible that there is a difference between the CJEN and table RPSCO?

 

Thank You