Hi experts.

 

We have a network activity and materials are assigned to that network activity. Now at the time of CN25 the backflushed materials are being consumed in the first confirmation, a parcial confirmation (PCNF). Is it a standard behavior? Why the materials are not consumed on the last confirmation (CNF)?

 

Best Regards