Budget at Level 5 WBS

$
0
0

Dear Experts

 

 

I have below 5 Levels of WBs elements

 

T-06425-01

T-06425-01-01

T-06425-02-01-01

T-06425-02-01-01-01

T-06425-02-01-01-01-01

 

 

If I want to allocate Budget directly at Level 5 WBS element in CJ30, system will automatically check Budget available at upper levels 4,3,2 and 1.

 

Once assigned in Levels 1,2,3,4 then only i can allocate the budget right?

 

No my quesion in standard do we have any option in directly giving budget at Level 5 only and save, If we do like this system will throw budget exceeded at upper levels of WBS.

 

 

 

 

Please Suggest.