Hi All,
I am facing an issue that on a WBSE whenever I create PR/PO the commitment budget is not getting generated on WBSE, means in CJI5 that particular line item is not visible. But PR/PO is generated and saved. Which should not happen, because commitments haven't generated.By doing some R&D, I found that it is happening due to incorrect GL entry in valuation class of material.
So what I want that system will restrict the PR/PO until the commitment getting generated against the WBSE. Please give your valuable suggestions.
Regards
Shishir