I am very new in SAP PS, I do not have knowledge as IT or Consultancy in ABAP. I have a situation and I need to propose something to the Bussiness/IT.
I need to see all detailed costs on Network actovity. We have some Networks with more activites; after working hours are booked we can see in CN41N an overall of total hours booked on each activity, but cost are only on Network level. I can see in CN48N detailed extract on Activity, but unfortunatelly it does not include any costs. It include all the informatin I need, but without costs.
Maybe there is not defned in the system to view total costs on Activity also in CN41N and can be defined? Maybe that can be extracted from a table from SE16?
Thank you!
Rodica