PR value is 130 , PO value is 85 - but budget exceeded

$
0
0

Dear All ,

 

The Service PR Value is 130 but PO was created for 85 only. But Budget is blocked for 130.

 

When I checked in CJ33 -- Availability Control Analysis. Its shows 130 only.

 

Any solution other than Technically Completing the activity, Because Service Entry Sheet is yet to be made.

 

 

Kindly help to rectify this problem.

Thanks in Advance.

Regards,

Shareeq