Quantcast
Channel: SCN : Popular Discussions - SAP Project Systems (SAP PS)
Viewing all articles
Browse latest Browse all 1010

Cancelled network activity confirmation but actual hours still capture

$
0
0

Dear all,

 

I have executed CN29 to cancel confirmation on the network activity and the status of the network activity is now REL, however there is 22.1 H still capture as actual and also there is forecast hours.

 

1.png

 

Could you please advise on this? How to remove the actual hours?

 

Thanks and regards,

Jessie


Viewing all articles
Browse latest Browse all 1010

Trending Articles



<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>